Ethereum’s Glamsterdam upgrade slips into 2027 over app risks
Ethereum developers now see late January or early February as the earliest realistic mainnet window for Glamsterdam, after gas changes put existing apps at risk.
The EthNews Desk3 min read

Ethereum’s Glamsterdam upgrade had been targeted for December. Core developers now say it cannot reach mainnet before mid-January, with late January or early February more realistic as app teams address contracts that could fail under its gas changes, according to CoinDesk’s report on the developers’ weekly meeting.
Why has Glamsterdam moved beyond its December target?
The delay follows scrutiny of two planned proposals, EIP-8037 and EIP-8038, which change how Ethereum charges for creating and accessing state. Under EIP-8037, the base charge for creating a contract would rise from 32,000 to 183,600 gas, with code storage charged separately. These changes are intended to make gas costs better reflect resource use.
The risk is that contracts written around current gas prices may run out of gas during a transaction after the repricing. That can happen when code relies on fixed gas stipends, hardcoded call limits or assumptions about how much gas remains. Some deployed contracts cannot be updated in place.
The Ethereum Foundation’s Glamsterdam testnet announcement describes repricing as part of a package that also includes enshrined proposer-builder separation and block-level access lists. The upgrade is designed to support greater layer-1 throughput. The Foundation advises developers to test contracts and gas estimation against the new rules.
Which apps and teams are affected?
Ethereum Foundation developer Marius van der Wijden estimated that as many as 15,000 programs could be disrupted, CoinDesk reported. The Foundation and outside security researchers said they had contacted more than 50 affected companies. Most told developers they could patch their software by mid-January if the repricing proceeds as written.
The impact is not uniform. The Foundation’s earlier impact analysis said most flagged issues could be fixed by increasing gas limits, and that the large majority of contracts were unaffected. Contracts that fail even with higher limits pose a harder problem, particularly if they are immutable or depend on a precise gas budget when calling another contract.
Client teams are split on whether the rules should change. Geth, Nethermind, Reth and ethrex favored proceeding with the current proposals, while Erigon continued to support changes. Besu accepted the current approach after pushing for a narrower fix.
What is the next milestone before mainnet?
Developers have tentatively penciled in a Hoodi test-network rehearsal for the week of Dec. 14. They are due to decide whether to proceed at their next meeting on Nov. 26. App makers have until mid-December to address their most serious issues and until Jan. 10 for less urgent fixes, according to the meeting discussion reported by CoinDesk.
That schedule replaces the earlier December target with a possible early-2027 mainnet launch. The extra time is tied to compatibility work and testing: developers are weighing whether existing contracts can keep operating under the new gas schedule without abandoning the repricing. A proposed workaround could create problems for a different set of apps, van der Wijden warned. The mainnet date remains unannounced; the Hoodi rehearsal and the outcome of contract fixes are the next checks on the path to activation.
Source material
- CoinDesk’s report on the developers’ weekly meeting — coindesk.com
- Glamsterdam testnet announcement — blog.ethereum.org