Skip to content
EthNews

News from across Ethereum

Ethereum’s Glamsterdam upgrade slips to 2027 as apps need fixes

Ethereum developers now see late January or early February as the likeliest Glamsterdam window, giving apps time to patch contracts exposed to proposed gas repricing.

The EthNews Desk3 min read

Ethereum’s Glamsterdam upgrade slips to 2027 as apps need fixes

Glamsterdam had been targeted for December. Ethereum developers now say the upgrade cannot reach mainnet before mid-January, with late January or early February more likely, as app teams fix contracts that could fail under its proposed gas rules.

At the developers’ weekly meeting, the Ethereum Foundation and outside security researchers said they had contacted more than 50 affected companies. Most told them they could patch their code by mid-January if the rules remain unchanged, CoinDesk reported from the meeting. The date remains tentative: testing must still be completed, and developers have yet to make a final decision on the next testnet rehearsal.

What in Glamsterdam could make contracts fail?

The risk comes from EIP-8037 and EIP-8038, which change how Ethereum charges for creating and accessing persistent state. Under the proposed rules, the base gas charge associated with deploying a smart contract rises from 32,000 to 183,600, with separate charges for storing its code.

That change reflects the long-term database cost of adding permanent data. Ethereum’s Glamsterdam roadmap describes the gas repricing as part of an effort to make state creation costs reflect the data added to the network. The broader upgrade is designed to increase Ethereum’s capacity, including by reorganising transaction processing.

But existing contracts may depend on the old costs. A contract that forwards a fixed gas allowance to another program, or assumes deployment and storage operations will cost roughly what they did before, can run out of gas during a transaction under the new schedule. That can make an operation fail even when the code itself has not changed.

Which apps and teams are affected?

Ethereum Foundation developer Marius van der Wijden estimated that as many as 15,000 programs could be disrupted. A separate review by security firms identified about 200 potential problems, according to CoinDesk’s reporting. The estimate does not mean all those contracts will fail; it identifies programs that may need review or changes under the proposed rules.

The concern reaches beyond new deployments. Some affected contracts may be difficult or impossible to update in place, while applications that can be patched still need time to test changes against the revised gas costs. The Foundation and researchers have been contacting companies to identify issues before the upgrade reaches the main network.

How does the delay change the upgrade plan?

The previous December target has given way to mid-January as the earliest possible mainnet activation. Developers are tentatively planning a Hoodi testnet rehearsal for the week of Dec. 14. They expect to decide at their Nov. 26 meeting whether to proceed with that test. App teams have until mid-December to address the most serious issues and Jan. 10 for less urgent fixes, according to the meeting discussion.

Most Ethereum client teams currently favor keeping the rules as proposed. Geth, Nethermind, Reth and ethrex supported proceeding without changes; Erigon still wants changes, while Besu accepted the current approach after pressing for a narrower fix. The timing therefore depends on both application readiness and testing: unlike the earlier December plan, the current expectation allows teams weeks to patch before mainnet activation.

Source material